April 20, 2005

  • Discuss Work Plan through October 15
  • Status on Backlog and Questionaire Mailing
  • Discuss Draft Plan ("Strawman")
  • Conservation Elements for Inclusion in Draft Plan

May 26, 2005

  • Review Revised Strawman
  • Discuss Baseline Criteria for Surface Water Model
  • Review Technical/Historical Sections of Draft Plan
  • Introduction/Background on Groundwater Model

June 27, 2005 – full day meeting

  • Presentation/Discussion of Groundwater Model
  • Review Revised Strawman

July 2005 – full day meeting

  • Questions/Issues on Groundwater Model
  • Relation to Surface Water Model
  • Review Draft Strawman for Additional Subareas

August 2005 – full day meeting

  • Review Revised Strawman
  • Begin Discussions on Legislative/Rule-making Recommendations

September 2005 – full day meeting

  • Finalize Legislative Recommendations
  • Final Comments and Review of Draft Plan

October 2005 – First Week

  • Review of Final Draft Plan Prior to Public Distribution

October 2005 – Second Week (No Later Than Friday October 14, 2005)

  • Final Plan Due to DNR Board and Out for Public Comment

 

To view and print the PDF documents on this site, the FREE Adobe Acrobat Reader is required. Click on the Adobe logo below to download it.

Get Acrobat Reader


Flint River Basin Plan
Georgia Environmental Protection Division
2 Martin Luther King Jr. Drive, Suite 1152 East Tower Atlanta, GA 30334
Telephone: 404.657.5947 or 888.373.5947 (toll-free throughout Georgia)
Copyright © 2004 by the Georgia Department of Natural Resources. All rights reserved.